Reports:
Affordable mass transit - guidance
This Report has also been made available in Adobe Acrobat format for downloading.
The Adobe® Acrobat Reader® can be freely downloaded.
Viewers with visual difficulties may find it useful to investigate services provided to improve the accessibility of Acrobat documents - www.adobe.com/accessibility/index.html
|
Foreword
Executive summary
1: Introduction
2: Phase 1 - strategic assessment
3: Phase 2 - scheme identification
4: Phase 3 - scheme refinement and monitoring
5: Data
Appendices
Foreword
The laudable aims of Transport
2010, whereby 25 new light rail
lines were envisaged by 2010,
have not materialised. Currently
there are 7 urban centres served
by a light rail system, and,
according to National Audit
Office, 4 of these are running
at a loss. The government now
considers that the construction
of 25 new lines might not be
practicable, offer value for money, or be affordable,
and it has recently withdrawn final approval for 3
proposed schemes because of escalating costs. What
has happened?
The problems of cost escalation, risk and associated
premiums, lengthy planning processes and inaccurate
patronage forecasting have been well documented
by the Parliamentary Select Committee . In particular,
the Select Committee notes that local authorities
have largely been left to decide whether light rail was
appropriate for their areas, and recommends a more
proactive role for government.
It is against this background that CfIT commissioned
its Affordable Mass Transit study. It is not our intention
to single out any one scheme or mode. It is our
intention to encourage better analysis to enable early
decision making and avoid delay and prevarication.
This is a useable, practical guide to delivering the
most appropriate mass transit system in a given
situation. As such it is aimed primarily at public
authorities and those with responsibility for transport
in urban areas. The focus is on all mass transit
technologies which we consider likely to provide
realistic, practical and affordable solutions in the
UK context.
Our approach puts forward a rigorous evaluation
designed to eliminate the less suitable options
from an early stage. In particular, it encourages the
continual assessment and monitoring of risk from
the initial, strategic assessment phase right through
to design and implementation. Most importantly, it
provides the option to reappraise at all stages, where
key parameters such as system costs or patronage
forecasts have changed. As such it is vital that
alternatives are genuinely optimised.
The CfIT study is designed to complement existing
guidance and provides advice on its application. In
so doing, we hope that our work will be of benefit
to both local authorities and DfT in their moves to
develop and support innovative local plans to tackle
congestion, as announced by the Secretary of State in
July of this year.
This study has been steered by a working group
comprising CfIT membership and local authority,
operating company and DfT representation.
In addition we have sought input from a wider
stakeholder group at key points in the project. I would
like to thank all involved for their input and support.
Ultimately, we hope that our work will go some way to
assisting the delivery of high quality mass transit that
provides value for money both in terms of the user
and non user benefits of the system.
Peter Hendy
Chair
Commission for Integrated Transport
September 2005
Executive summary
The need for this guidance
The need for this guidance has arisen from:
- the Government's objectives for
transport, notably the need to reduce
reliance upon the private car;
- the lower than anticipated rate of
delivery of mass transit systems;
- concerns regarding the affordability
and below forecast performance of
some mass transit schemes that have been
promoted or delivered in recent years; and
- the consequent need to achieve
improved delivery of affordable and costeffective
mass transit systems.
Purpose of this guidance
This guidance document is designed to assist
promoters of mass transit systems to select
the most suitable, affordable and costeffective
technology to meet their needs and
objectives, and to do so quickly and at reasonable
cost.
For the purposes of this guidance mass transit is
defined as an urban public transport system which
provides a 'turn-up and go' service. This requires a
maximum headway between vehicles of 10 to 15
minutes or a minimum frequency of 4-6 services
per hour over core sections of route, providing a
minimum capacity per direction of typically 300
passengers per hour (pph) for bus based systems and
800 pph for rail based systems.
In addition it is assumed that mass transit systems as
addressed by this guidance will enjoy a degree of
segregation from, and/or priority over, general traffic
movements, unless these can be controlled effectively
through measures such as road user charging.
Affordability relates to the ability to deliver the system.
This includes the ability to obtain adequate funds
for the construction and operation of the system
(including any requirement for ongoing revenue
support), the availability of such funding within an
appropriate timescale, and the balance between
system costs and the benefits delivered. Where private
sector financing is to be used the financial assessment
must include the costs and charges associated with
such finance.
The process detailed in this guidance is intended to
address all potential mass transit technologies that
are capable of providing a 'turn up and go' service.
The focus of the detail of this guidance (in terms of
the information supplied) is upon bus based and light
rail technologies, as these are most likely to provide
realistic, practical and affordable solutions in the UK
context.
Users of the guidance
The primary audience for this guidance will be
those directly responsible for the promotion
of mass transit systems. These will typically be
public authorities with responsibility for transport in
major urban areas, such as County, City, Regional
and Unitary councils, Passenger Transport Authorities
and TfL. The guidance should be used by the
elected members and officers of these organisations
together with those working on their behalf (such as
consultancy companies).
The secondary users of this guidance will be
those organisations associated with, but not directly
responsible for, the promotion of mass transit
schemes. This will include those providing public
sector finance (such as DfT), private sector financial
organisations, PFI contractors and public transport
operators. This guidance is intended to assist such
organisations (and those working on their behalf)
to determine whether the work undertaken by the
promoting authority is robust and in accordance
with best practice and whether the proposed system
represents a sound investment.
Approach to this guidance
This guidance is focused upon the UK context
and is designed to link closely to existing guidance
relating to the promotion of mass transit systems
within the UK. In particular, it is presumed that the
overall context and objectives for any mass transit
system have already been clearly established through
the Regional Transport Strategy or Local Transport
Plan process, together with identification of the overall
planning and transport context within which the
system will operate.
The guidance is designed to provide an overall
structure for the decision making processes
needed to deliver the most appropriate mass transit
system for a given situation. It explains the nature
of the decisions that should be made and provides
information to support the decision making process.
This guidance is not prescriptive. It is intended to
encourage quick and efficient assessment of a wide
range of mass transit systems and technologies
and the geographic areas over which these may be
applied. In particular, careful consideration should
be given to the differences between lower intensity
solutions applied on an area-wide basis and higher
intensity solutions applied on a corridor basis.
Structure
The structure detailed in this guidance uses
increasing levels of detail in a step-wise manner to
progressively eliminate those options that
are not likely to provide an 'affordable'
solution to the identified need and objectives. Three
principal phases of work are identified as shown in
Figure 1:
- Phase 1 - a high level strategic
assessment of the alternative mass transit
technology options and geographic areas of
treatment;
- Phase 2 - a detailed appraisal of a
shortlist of options in accordance with the
recommendations set out in the Government's
Major Scheme Appraisal Guidance; and
- Phase 3 - a monitoring process to
be adopted during the detailed design and
implementation of the preferred option.
Assessment of risk is an important part of the process
throughout all three Phases. Allowance should be
made for variability in key parameters (particularly
costs and forecast patronage), with higher levels of
allowance in the earlier Phases reflecting the less
detailed analysis and thus lower levels of definition
and certainty. Sensitivity tests are an essential part
of the evaluation of risk and are recommended at
key points in the process. In addition, optimism bias
should be included at all stages in accordance with
guidance from DfT.
The focus of the guidance is on Phase 1 - the
process of selecting the most appropriate options for
detailed analysis from a wide range of mass transit
technology options including area-wide or corridor
based treatment. Promoters must assess whether
their transport objectives can be best met by applying
intensive measures to a limited number of corridors
(for example via rapid transit measures) or whether
more widespread application of lower level measures
may be more effective. The key output of this phase
should be a clear demonstration that all options
have been considered together with robust and
transparent evidence as to the reasons for rejection of
options. This Phase will help ensure that only the most
appropriate options are taken forward for detailed
assessment in Phase 2.
Where the more detailed work in Phases 2 or 3
results in significant changes to key system parameters
(such as scheme costs or performance), consideration
should be given to the need to re-examine the earlier
Phase(s), as illustrated in Figure 1. Such iteration
will be required where the changes are of a scale
that would affect the decisions made in the previous
Phase(s). This is most likely to occur as a result of
increases in estimated system costs or reductions in
forecast patronage.
Figure 1: Guidance overview

Phase 1
The Phase 1 process comprises 3 steps, each of these
steps is briefly summarised below:
Step 1 - a qualitative assessment of the
performance of each technology option. This
is undertaken through identification of:
- the Problems that the mass transit
system is intended to address;
- the Policy Objectives to which the
mass transit is intended to contribute;
- the Context within which the mass
transit system will be implemented
and operated; and
- the Physical Opportunities
and Constraints that will influence
the design of the mass transit system.
Indicators should be established for each of
these areas and the performance of each
option assessed qualitatively using a 7-point
scale.
The results of the qualitative assessment
should enable elimination of the those options
that do not provide an effective solution to
the identified problems, do not contribute
significantly to the policy objectives, or are
unlikely to be deliverable.
Step 2 - a high-level quantitative
assessment of the financial
performance of each technology option.
This is undertaken through identification of:
- likely levels of passenger demand;
- revenue;
- operating costs; and
- capital costs.
An outline methodology is indicated in
the guidance, together with supporting
information to assist the estimation of system
costs. The detail of the work in Step 2 should
be tailored to a level sufficient to distinguish
between the options being examined and thus
inform the decisions being made. Allowance
should be made for risk, with sensitivity tests
recommended to establish the impact of
variation in key system parameters.
The results of Step 2 should enable
rejection of further options where these are
unaffordable in the sense that insufficient
funding is likely to be available within an
appropriate timescale to support the required
level of capital expenditure and/or operating
subsidy.
Step 3 - a value for money
assessment of each technology option
based upon the results of Steps 1 and 2.
The quantitative work undertaken in Step 2
should enable refinement of the qualitative
assessment, in particular a better estimation
of the benefits likely to be delivered by each
option.
A Technology Option Appraisal
Summary Table (TOAST) should be
assembled to include the key indicators
arising from the results of Steps 1 and 2.
This Appraisal Summary Table (AST) is based
upon the advice given in DfT's 'Guidance on
the Methodology for Multi-Modal Studies'
(GOMMMS). Emphasis should be given
to those indicators that provide distinction
between alternative options and will thus
contribute to the decision making process. The
TOAST should also include an estimate of the
risks associated with each of the elements in
the table.
On the basis of the TOAST, the remaining
options should be ranked on a value-formoney
basis. This will require comparison of
the benefits, impacts and costs associated with
each option. The 'best' performing options as
assessed by the TOAST process will be taken
forward to more detailed analysis in Phase 2.
It is recommended that an independent
review of the Phase 1 process be undertaken
at the end of Step 3. This should be designed
to ensure that the full range of options has
been considered and that the assessment
process has been undertaken in a manner that
is both appropriate and robust.
Phase 2
Phase 2 focuses on scheme development and
appraisal. This area is covered by the DfT's existing
detailed guidance and thus this guidance does not
seek to replace, supersede, or duplicate that existing
guidance.
Thus Phase 2:
- indicates the existing guidance
framework for scheme development and
appraisal;
- explains the linkages between Phase 1 of
this guidance and the existing guidance; and
- provides advice on the application of the
existing guidance.
The results of the Phase 2 activity should be
compared against the outputs from Phase 1 to
determine the degree to which key system values may
have changed during the more detailed assessment
process in Phase 2. This review should examine
whether the changes in such values (in particular
costs and patronage) would be sufficient to alter the
conclusions from Phase 1. Where this is the case,
the Phase 1 work should be repeated using the more
detailed valuations from Phase 2 and, if appropriate,
alternative option(s) taken forward to Phase 2.
The output from Phase 2 should be a definition
for the preferred scheme option(s), the next best
option and a low cost alternative together with
their appraisal summary tables. These should be
complemented by the results of sensitivity tests to
inform the monitoring activity in Phase 3.
Phase 3
The Phase 3 process comprises monitoring
of both internal and external changes
that may occur during the detailed design and
implementation of the preferred system. Internal
changes are those occurring as part of the scheme
design and refinement process. External changes
are those occurring to the external context within
which the system will be implemented and operated.
An important part of this monitoring process will be
to ensure that the conclusions reached in
Phase 1 and 2 continue to be valid. Where
changes to key system values (in particular system
costs and forecast patronage) remove the advantage
previously shown for the preferred option, it will be
necessary to repeat Phase 2 and, where appropriate,
Phase 1 using the revised valuations.
Separate but related detailed monitoring plans are
recommended:
- Internal Changes - should be recorded as
they occur. The nature of each change should
be recorded together with its impacts upon
system performance and any recommended
action; and
- External Changes - should be recorded
on a periodic basis in a similar manner to
internal changes.
It will be important to undertake regular assessments
of the cumulative impacts of the changes that
have been monitored. It should be noted that the
net effect of a series of changes may be greater than
the sum of the individual effects for each change. As
noted above, particular attention should be given to
system costs and forecast patronage.
The results of the monitoring process should lead to
decisions regarding the future development of the
scheme, these are likely to fall into three categories:
- changes to scheme design to
accommodate or mitigate the change;
- the promotion of changes to the external
environment (particularly where these are
under the control of the system promoter); and
- in circumstances where changes to key system
values have required a return to Phase 2
or Phase 1, change to an alternative
scheme or technology option.
Data
As part of this guidance, technical data is
provided to assist with the quantitative
calculations required, particularly those outlined in
Step 2 of Phase 1. The appendices to the guidance
provide details of capital costs and operating
costs for a number of existing and proposed mass
transit systems in the UK. Recorded costs vary
significantly and are strongly influenced by
the context within which an individual scheme is
being promoted. There is a general lack of robust
data relating to bus-based schemes due to:
- a relative lack of experience of measures such
as guided bus;
- a lack of detailed monitoring of enhanced bus
based systems; and
- the commercial confidentiality attached to
bus-based cost information.
The data sources that have been researched
emphasise the need for a systematic approach to
mass transit system monitoring and data collection
in order to provide information that will enhance the
robustness of quantification of costs and performance
for mass transit systems. It is recommended
that DfT give serious consideration to
a programme of data collection and
monitoring for mass transit systems (similar
to that adopted by the Highways Agency for trunk
road schemes), including those using bus based
technology. In particular there is a lack of data
relating to bus systems that have been subject
to intensive investment (such as Crawley
'Fastway' and the guided bus systems in Leeds and
Bradford) and this is an important area for improved
data collection.
[ Previous ]
[ Contents ]
[ Next ]